TY - JOUR
T1 - Laboratory and numerical investigation of integral abutment connections with pile couplers
AU - DeJong, Austin
AU - Shi, Weizhuo
AU - Shafei, Behrouz
AU - Hosteng, Travis
N1 - Funding Information:
The support of Accelerated Bridge Construction University Transportation Center (ABC-UTC) and Iowa Department of Transportation (Iowa DOT) is gratefully acknowledged. The authors would like to also acknowledge the technical assistance of Dr. Brent Phares and Dr. Shahin Hajilar, as well as the laboratory assistance of Mr. Doug Wood and Mr. Owen Steffens.
Publisher Copyright:
© 2021 Elsevier Ltd
PY - 2021/12/1
Y1 - 2021/12/1
N2 - By benefiting from precast structural elements, accelerated bridge construction (ABC) strategies have received growing attention, as they can alleviate the consequences of prolonged bridge closures caused by cast-in-place (CIP) construction methods. Among various precast elements, integral abutments are commonly employed to eliminate the expansion joint between a bridge's substructure and superstructure, where the ingress of aggressive ions often requires frequent maintenance and repair. Due to the heavy reinforcement required at the bridge end region, congestion issues often arise, especially when attempting to utilize ABC. To address such issues, this study focuses on the integral abutment connection details designed with a set of pile couplers that splice the integral abutment diaphragm to the pile cap. The investigations involve full-scale laboratory experiments conducted to understand the structural response of the proposed connection details under both thermal and live loads. The main response measures obtained from the conducted tests were then compared to those recorded during a full-scale test on a CIP integral abutment with the details that represented the conventional design and construction practices. Upon completing the laboratory investigations, a series of numerical simulations were performed to evaluate the most critical connection details. The simulations explored a range of steel sections and a proposed design revision, in which the pile couplers were replaced with a bar reinforcement cage. The outcome of this study helps the bridge industry effectively use pile couplers for integral abutment connections, especially for ABC applications.
AB - By benefiting from precast structural elements, accelerated bridge construction (ABC) strategies have received growing attention, as they can alleviate the consequences of prolonged bridge closures caused by cast-in-place (CIP) construction methods. Among various precast elements, integral abutments are commonly employed to eliminate the expansion joint between a bridge's substructure and superstructure, where the ingress of aggressive ions often requires frequent maintenance and repair. Due to the heavy reinforcement required at the bridge end region, congestion issues often arise, especially when attempting to utilize ABC. To address such issues, this study focuses on the integral abutment connection details designed with a set of pile couplers that splice the integral abutment diaphragm to the pile cap. The investigations involve full-scale laboratory experiments conducted to understand the structural response of the proposed connection details under both thermal and live loads. The main response measures obtained from the conducted tests were then compared to those recorded during a full-scale test on a CIP integral abutment with the details that represented the conventional design and construction practices. Upon completing the laboratory investigations, a series of numerical simulations were performed to evaluate the most critical connection details. The simulations explored a range of steel sections and a proposed design revision, in which the pile couplers were replaced with a bar reinforcement cage. The outcome of this study helps the bridge industry effectively use pile couplers for integral abutment connections, especially for ABC applications.
KW - Bar Reinforcement Cage
KW - Finite-Element Simulation
KW - Full-Scale Structural Test
KW - Integral Abutment Connection
KW - Pile Coupler
UR - http://www.scopus.com/inward/record.url?scp=85116014621&partnerID=8YFLogxK
U2 - 10.1016/j.engstruct.2021.113159
DO - 10.1016/j.engstruct.2021.113159
M3 - Article
AN - SCOPUS:85116014621
SN - 0141-0296
VL - 248
JO - Engineering Structures
JF - Engineering Structures
M1 - 113159
ER -