Bi-objective optimisation model for installation scheduling in offshore wind farms

Research output: Journal PublicationArticlepeer-review

Abstract

A bi-objective optimisation using a compromise programming approach is proposed for installation scheduling of an offshore wind farm. As the installation cost and the completion period of the installation are important aspects in the construction of an offshore wind farm, the proposed method is used to deal with those conflicting objectives. We develop a mathematical model using integer linear programming (ILP) to determine the optimal installation schedule considering several constraints such as weather condition and the availability of vessels. We suggest two approaches to deal with the multi-objective installation scheduling problem, namely compromise programming with exact method and with metaheuristic techniques. In the exact method the problem is solved by CPLEX whereas in the metaheuristic approach we propose Variable Neighbourhood Search (VNS) and Simulated Annealing (SA). Moreover, greedy algorithms and a local search for solving the scheduling problem are introduced. Two generated datasets are used for testing our approaches. The computational experiments show that the proposed metaheuristic approaches produce interesting results as the optimal solution for some cases is obtained.

Original languageEnglish
Pages (from-to)393-407
Number of pages15
JournalComputers and Operations Research
Volume78
DOIs
Publication statusPublished - 1 Feb 2017
Externally publishedYes

UN SDGs

This output contributes to the following UN Sustainable Development Goals (SDGs)

  1. SDG 7 - Affordable and Clean Energy
    SDG 7 Affordable and Clean Energy

Free Keywords

  • Compromise programming
  • Installation scheduling
  • Multi-objectives
  • Offshore wind farm
  • Simulated Annealing
  • Variable Neighbourhood Search

ASJC Scopus subject areas

  • General Computer Science
  • Modelling and Simulation
  • Management Science and Operations Research

Fingerprint

Dive into the research topics of 'Bi-objective optimisation model for installation scheduling in offshore wind farms'. Together they form a unique fingerprint.

Cite this